Ken-Ton Union Free School
District
May 7, 1999
Prepared By:
Town of Tonawanda Technical Support Department
2919 Delaware Ave.
Kenmore, NY 14217
INTRODUCTION
The Town of Tonawanda converted an existing Wide Area Network (WAN) from a telephone company (Telco) that provided a leased line configuration to a spread spectrum radio frequency configuration. The WAN is used for transmission of data and computer access. The conversion was prompted by high recurring Telco charges, WAN unreliability and the ability to improve network traffic throughput. The project is anticipated to save approximately $65,000 per year in the elimination of Telco charges alone.
The possibility of including the Ken-Ton School District in the project presented itself due to the opportunity to share services and potentially receive grant money to help offset the costs related to WAN conversion. The inclusion of the district with the town project consisted of:
§ Sharing the new Police antenna tower at 1835 Sheridan Dr. as a repeater site and radio frequency focal point
§ Conducting a line of site analysis for three school buildings
§ Designing and installing a Wireless WAN based for those three school buildings
This work related to the school was included in the town's project as a separate bid item to help differentiate costs for each entity.
PROJECT
DESCRIPTION
Town of
Tonawanda
The project involved the conversion of one T-1, two 56 kbps and ten ISDN Telco connections with a 2.4 GHz, 11.0 Mbps, Spread Spectrum Radio Frequency wireless WAN. The 14 municipal buildings included in the WAN are as follows:
|
Aquatic and Fitness
Center |
1
Pool Plaza, 14223 |
|
Brighton Golf
Course |
70
Brompton Rd., 14150 |
|
Development
Corporation |
3411
Delaware Ave.,14217 |
|
Highway
Department |
450
Woodward Ave., 14150 |
|
Mang
Park Youth Center* |
135
Wilbur Ave., 14217 |
|
Municipal
Building |
2919
Delaware Ave, 14217 |
|
Youth, Parks and Recreation
Department |
2440
Sheridan Dr., 14223 |
|
Police/Paramedics/Fire/Court |
1835
Sheridan Dr., 14223 |
|
Senior Citizen's
Center |
291
Ensminger Rd., 14150 |
|
Sheridan Golf
Course |
490
East Park Dr., 14150 |
|
Parkside Village Community
Center |
169
Sheridan Parkside Dr., 14150 |
|
Wastewater Treatment
Facility |
779
Two Mile Creek Rd. 14150 |
|
Water and Sewer/Building
Departments |
525
Belmont Ave., 14223 |
|
Water Treatment
Plant |
218
Aqua Lane, 14150 |
* The youth center at Mang Park will be an addition to the existing WAN.
Actual work performed by the contractor included:
· Preliminary and Physical Line of Sight Analysis
· Antenna design and installation based on sight conditions
· An additional antenna tower was required at Sheridan Golf course due to line of site constraints
· Installation of wireless bridges
· Cabling between antennas and wireless bridges based on sight conditions
· System testing
· Two year maintenance and two spare radio units
Town forces performed additional work as follows:
· Install power source to wireless bridge location
· Install Category 5 Ethernet cable between existing LAN's and wireless bridge
· Reconfigure network settings, IP addressing and subnets
· Remove existing ISDN modems, ISDN Portmaster, CSU/DSU's and routers from service
· Terminate leased line connections with Bell Atlantic
The scope of work related the District consisted of necessary preliminary steps to convert three existing Telco based connections to a wireless WAN configuration. As previously stated, the primary benefit to the school is the use of the tower at the Police Station and the opportunity to gain a Telco to wireless conversion plan using the town's contractor.
Originally, the District planned on just performing a line of site analysis and wireless WAN design for all of their 14 buildings, however the actual work performed by the contractor included:
· Preliminary and Physical Line of Sight Analysis premised on using the tower at the Police Station and Holmes School and the Administration Bldg.
· Wireless WAN design based on line of site conditions and operation at a radio frequency of 2.4 GHz
· Antenna design and installation based on sight conditions
· Installation of wireless bridges at Police and three School Buildings. Bridge at Police acts as root device in the multi point Scholl WAN.
· Cabling between antennas and wireless bridges based on sight conditions
· System testing
· Two year maintenance
The 3 school buildings to be included in the design are listed below:
|
Administration Bldg. (has fiber optic cable connection to Hoover Elem. & Middle @ 249 Thorncliff Rd.) |
1500 Colvin Blvd., 14223 |
|
Holmes Elementary |
365 Dupont Ave., 14150 |
|
Philip Sheridan Building |
3200 Elmwood Ave., 14217 |
The town's network is physically separate from the District's and operates independently.
COORDINATION
To simplify the Shared Services grant application and the grant award, the town acted as the project leader.
PROJECT REPRESENTATIVES
The town Engineering Department would act as Project Managers and liaison between the State, Grant Manager, School District and the town.
|
Name |
Charge |
Agency |
Address |
Telephone
Fax |
email |
|
James
Jones |
Project
Leader |
Town |
2919 Delaware Ave.,
Kenmore, NY 14217 |
877-8805
871-8840 |
|
|
Sue
Barnes |
Grant
Adm. |
Grantmakers
Advantage, Inc. |
7 Marina Park South., Buffalo, NY 14202 |
870-2526 842-6123 |
|
|
Rich
DeGlopper |
Liaison |
Ken-Ton |
3200 Elmwood Ave.,
Kenmore, NY 14217 |
874-8484
874-8518 |
rich_deglopper@admgat.kenton.k12.ny.us
|
ACCOUNTING SUMMARY
|
Original project estimate - Town work only |
$115,000.00 |
|
Original Contract Award to Transwave Communication Systems, Inc. - Town work only |
$112,500.00 |
|
Change order to Transwave for additional antenna tower at Sheridan Golf course |
$2,738.00 |
|
Change order to Transwave for District work |
$30,550.00 |
|
Total Contract Amount for Transwave |
$145,788.00 |
PROJECT
TIMELINE
|
Date |
Description |
|
11/09/98 |
Town advertises for bids to construct Wireless Wide Area Network for town as well as alternate bids related to desired work by District |
|
11/13/98 |
Town submits grant application to NYS for SSSP |
|
12/01/98 |
Town receives bids from three vendors |
|
12/21/98 |
Town awards contract to Transwave for town work only for an11 MBps wireless WAN |
|
1/25/99 |
Contract executed by town |
|
1/26/99 |
Contractor begins work for town installing antenna at Police station |
|
1/29/99 |
Town receives notification from NYS regarding grant approval |
|
3/22/99 |
Town executes Intermunicipal Agreement with Ken-Ton School District |
|
3/22/99 |
Town approves change order to Transwave to proceed with work for School District |
|
3/30/99 |
Substantial completion of town work by Transwave |
|
4/16/99 |
Town switches to new wireless WAN |
|
4/26/99 |
Contractor begins work for District |
|
5/4/99 |
Substantial completion of District work by Transwave |